A Builder’s Guide to Progress Payments in Queensland
Your Right to Get Paid
If you're a builder, tradie, or subcontractor in Queensland, getting paid on time isn't just important, it's essential to keeping your business alive. Late payments, disputed invoices, and cash flow problems are among the biggest threats facing construction businesses today.
The good news? Queensland law gives you powerful rights to secure payment for your work. The Building Industry Fairness (Security of Payment) Act 2017 (BIF Act) was specifically designed to help people like you get paid faster and more reliably.
At Odyssey Legal, we have helped countless builders, contractors, and trades recover significant amounts in unpaid invoices. This guide explains your rights in plain language and shows you exactly how to use them to protect your business.
Why This Matters to You
Every day you wait for payment is a day your business suffers. You have got:
- Staff wages to pay.
- Suppliers demanding payment.
- Equipment finance and overheads.
- Your own bills to cover.
The BIF Act levels the playing field. It gives you legal weapons to fight back against slow payers and payment disputes, including:
- The right to claim progress payments, even if your contract doesn't mention them.
- Fast-track adjudication that delivers decisions in weeks, not years.
- The ability to suspend work if you're not paid.
- Mechanisms to get paid from parties higher up the contractual chain.
Let's break down exactly how to use these rights.
Understanding Your Statutory Right to Payment
What Counts as 'Construction Work'?
The BIF Act covers a broad range of work, including:
- All building, renovation, and demolition work.
- Excavation, earthworks, and site preparation.
- Installation of electrical, plumbing, HVAC systems.
- Concreting, bricklaying, carpentry, and all trades.
- Scaffolding and temporary works.
- Site cleanup and restoration.
- Supply of materials and equipment for construction.
- Design services, engineering, and architectural work.
- Plant and equipment hire.
If you are doing any of this work in Queensland, you are generally covered.
Important Exclusions
The BIF Act doesn't apply to:
- Small residential jobs under $3,300 (indexed annually) where you're dealing directly with a homeowner.
- Work performed outside Queensland.
- Standard employment relationships (you need to be an independent contractor).
How to Claim Your Progress Payments
Getting paid starts with issuing a proper payment claim. This is not just an invoice (it is a legal document that triggers specific rights and obligations).
What Makes a Valid Payment Claim?
Your payment claim must tick all these boxes:
1. Put it in writing
- Email is perfectly fine.
- Formal letters work too.
- Keep proof of when you sent it.
2. Say it is a payment claim under the Act
- Include this exact phrase: "This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017".
- This is crucial (without it, you might not be able to use the Act's protections).
3. Clearly identify the work
- Describe what work you've completed.
- Reference the contract or purchase order.
- Include dates when work was performed.
- Attach photos if helpful.
4. State the amount you're claiming
- Break down the calculation clearly.
- Include GST separately.
- Show any variations or extras.
- Deduct any previous payments received.
- You can include interest on overdue amounts.
5. Demand payment
- State when payment is due (per your contract terms).
- Provide your payment details.
6. For Head Contractors: Include a Supporting Statement
- Declare whether you have paid all your subbies.
- If not, explain why and provide details.
- Failing to do this (or lying in it) can result in serious penalties.
Example Payment Claim Template
Here's a simple structure you can follow:
PAYMENT CLAIM
To: [Recipient's name and address]
From: [Your business name and ABN]
Date: [Date]
Project: [Project name/address]
Contract: [Contract reference]
NOTICE: This is a payment claim made under the Building Industry Fairness
(Security of Payment) Act 2017.
Work Completed:
[Detailed description of work completed since last claim]
Amount Claimed:
Labour: $[amount]
Materials: $[amount]
Variations: $[amount]
Subtotal: $[amount]
GST: $[amount]
TOTAL CLAIMED: $[amount]
Less previous payments: $[amount]
AMOUNT NOW DUE: $[amount]
Payment is due by: [date - typically 10-30 days per your contract]
Please make payment to:
[Bank account details]
Supporting Statement (if you're a head contractor):
[Declaration about subcontractor payments]
[Your signature]
[Your name and position] Critical Timing Rules
When can you claim?
- You can claim at regular intervals called "reference dates".
- These are either specified in your contract or default to monthly (last day of each month).
- You can only make ONE payment claim per reference date.
How soon must you claim?
- Within 6 months after you last did the work (or sooner if your contract specifies).
- Within 6 months after completing all work under the contract.
Why timing matters:
- Miss these deadlines and you lose your right to use the BIF Act's powerful enforcement tools.
- You might still be able to sue for breach of contract, but that is slower and more expensive.
Top Tip: Claim Regularly
Don't wait until you've finished the whole job to claim payment. Issue payment claims:
- Monthly, if possible.
- At key milestones.
- As soon as practical completion is achieved.
Regular claiming keeps cash flowing and reduces your exposure if things go wrong.
What Happens After You Issue a Payment Claim?
Once you have issued your payment claim, the ball is in their court. The other party has three options:
Option 1: Pay You in Full
Perfect! This is what should happen. If they pay the full amount by the due date, everyone's happy and the job continues.
Option 2: Issue a Payment Schedule
If they want to dispute your claim or pay less than you've claimed, they must issue a "payment schedule" within 15 business days (or whatever shorter period your contract specifies).
The payment schedule must:
- Identify your payment claim.
- State how much they propose to pay (which might be zero).
- Explain in detail why they're paying less than you claimed.
- Include all their reasons for withholding payment.
This is critical: If they do not include a reason in the payment schedule, they cannot raise it later in adjudication or Court.
Option 3: Do Nothing
This is the worst move they can make, and the best outcome for you. If they do not pay you and do not give you a payment schedule within time, they automatically become liable to pay your full claimed amount.
You can then:
- Sue them in Court for the claimed amount (they cannot defend it).
- Apply for adjudication.
Taking It to Adjudication
If you are not getting paid, adjudication is your fastest and most powerful option. This is a rapid dispute resolution process that typically delivers a binding decision within two to three weeks.
When Can You Adjudicate?
You can apply for adjudication if:
Scenario A: They did not give you a payment schedule
- You issued a valid payment claim.
- They did not provide a payment schedule within 15 business days.
- They have not paid you the full claimed amount.
Scenario B: They gave you a payment schedule but did not pay
- You issued a valid payment claim.
- They gave you a payment schedule.
- They have not paid the scheduled amount by the due date.
Scenario C: They are disputing your claim
- You issued a valid payment claim.
- They gave you a payment schedule proposing to pay less than you claimed.
- You disagree with their valuation.
How Quickly Must You Act?
Strict deadlines apply:
If no payment schedule was given:
- You have 30 business days after the later of:
- The due date for payment, or
- The last day they could have given you a payment schedule.
If a payment schedule was given:
- 20 business days after the due date for payment (if they did not pay), or
- 30 business days after receiving the payment schedule (if disputing).
Miss these deadlines and you lose your right to adjudicate that claim.
How to Apply for Adjudication
Step 1: Prepare Your Application
Gather all documents:
- Your payment claim
- Proof you served it on them
- Any payment schedule you received
- The contract
- All supporting documents (invoices, delivery dockets, photos, timesheets, etc.)
- Your written submissions explaining why you're entitled to the claimed amount
Step 2: Lodge with the QBCC
Submit your application to the Queensland Building and Construction Commission's Adjudication Registry, including:
- The completed application form
- All supporting documents
- The application fee (currently varies based on claim value)
Step 3: Serve on the Respondent
Immediately after lodging, you must serve a complete copy of your application on the other party.
Step 4: An Adjudicator is Appointed
The QBCC Registrar appoints an independent, qualified adjudicator from their register. The adjudicator must:
- Be impartial
- Have relevant construction industry experience
- Have no conflict of interest
Step 5: The Other Party Responds (Maybe)
- If they gave you a payment schedule: They can lodge an adjudication response within 15 business days (or two business days after the adjudicator accepts the appointment, whichever is later)
- If they did not give you a payment schedule: They cannot lodge a response at all. You will almost certainly win.
Critical Rule: They can only include reasons in their adjudication response that were already in their payment schedule. Recent court cases have strictly enforced this rule (no new reasons allowed).
Step 6: The Adjudicator Decides
The adjudicator must make a decision within:
- 10 business days for standard claims
- 15 business days for complex claims
- Extended timeframes if both parties agree
The adjudicator will determine:
- How much you're entitled to be paid (the "adjudicated amount")
- When it must be paid (usually within 5 business days)
- What interest applies
- Who pays the adjudicator's fees
What If You Win?
Once the adjudicator issues their decision, the other party must pay you within five business days (or by whatever date the adjudicator specifies).
If they still do not pay, you can:
1. Suspend Work
- Give them two business days written notice
- Stop work until you are paid
- You are protected from liability for any losses they suffer
2. File the Decision as a Court Judgment
- Get an adjudication certificate
- File it with the Magistrates, District, or Supreme Court
- Enforce it like any other court judgment (garnishee orders, bankruptcy, etc.)
3. Register a Charge Over the Property
- If your work was done on land or a building, you can register a charge over that property
- This prevents them from selling without paying you
- It is like a lien on the property
4. Go After Someone Higher Up the Chain
- If the party who owes you is also owed money by someone else (like a head contractor)
- You can require that higher party to withhold funds and pay you instead
Real Case Example: What Happens When You Don't Follow the Rules
In a recent Queensland Supreme Court case (Bright Days Herston Pty Ltd v ATG Project & Property Solutions Pty Ltd [2025] QSC 147), the court reinforced just how seriously these rules are taken.
The case involved a payment dispute where the respondent tried to argue in the adjudication about payments they'd made after issuing their payment schedule. The court said this wasn't allowed—those were "new reasons" that hadn't been included in the payment schedule.
The lesson: If you're responding to a payment claim, include ALL your reasons in your payment schedule. If you're claiming payment, make sure you follow every procedural step correctly.
This case also confirmed that if an adjudicator becomes aware of a potential conflict of interest and doesn't issue a decision, the matter can be referred to a new adjudicator without you having to start from scratch with a new payment claim.
Powerful Enforcement Tool: Payment Withholding Requests
Here's a tool many builders don't know about. If you've won an adjudication but the respondent won't pay, you can look up the contractual chain.
How It Works
Let's say:
- You're a subcontractor (or subbie).
- Your contractor owes you $50,000 (adjudicated).
- Your contractor won't pay.
- But the head contractor owes your contractor $100,000.
You can serve a "payment withholding request" on the head contractor. This legally requires them to:
- Hold onto $50,000 of what they owe your contractor.
- Pay it to you instead.
- Not pay it to the contractor who owes you.
Benefits
- You get paid even when the party you contracted with is broke or refusing to pay.
- The head contractor is protected from double liability if they comply.
- You get a charge over the withheld amount.
- It's often more effective than trying to enforce against an insolvent contractor.
Requirements
To use this mechanism:
- You must have an unpaid adjudicated amount.
- You must identify the "higher party" and provide details.
- The respondent must give you information about higher parties if you request it.
Protecting Your Rights: Practical Tips for Builders
Based on years of helping builders recover unpaid money, here's Odyssey Legal's practical advice:
Before You Start Work
1. Get it in writing
- Always have a written contract, even for small jobs.
- Make sure payment terms are clearly stated.
- Understand your reference dates.
- Know your rights under the BIF Act.
2. Check who you're dealing with
- Verify they have a QBCC license (if required).
- Research their payment history if possible.
- Consider requesting bank guarantees or security for large jobs.
- Be cautious with new clients.
3. Set up proper systems
- Have a template payment claim ready to go.
- Create a system for tracking reference dates.
- Set up calendar reminders for claim deadlines.
- Keep meticulous records from day one.
During the Job
4. Document everything
- Take photos of work in progress.
- Keep daily diaries or site records.
- Retain all delivery dockets and invoices.
- Get written approval for variations BEFORE doing the work.
- Keep copies of all correspondence.
5. Claim regularly
- Don't wait until the end to claim.
- Issue payment claims monthly or at milestones.
- Follow up on overdue payments immediately.
- Don't let debts accumulate.
6. Maintain good records
- File copies of all payment claims.
- Keep proof of service (email receipts, registered post receipts).
- Track when payment schedules are due.
- Calculate deadlines and diary them.
7. Watch for warning signs
- Late payments becoming a pattern.
- Excuses and delays.
- Avoiding communication.
- Financial stress indicators.
When Problems Arise
8. Act quickly
- Don't wait and hope; problems rarely fix themselves.
- If no payment schedule arrives within 15 business days, consider your options immediately.
- Calculate your deadlines for adjudication applications.
- Get legal advice early.
9. Follow the process exactly
- Every step of the Act has strict requirements.
- One mistake can cost you your rights.
- Don't try to DIY adjudication without professional help.
- The stakes are too high to risk getting it wrong.
10. Consider your options strategically
- Adjudication vs. court proceedings.
- Suspending work vs. continuing.
- Negotiating settlement vs. pursuing full amount.
- Short-term cash flow vs. long-term relationship.
Getting Paid
11. Enforce decisions promptly
- Don't wait if they don't pay after adjudication.
- Use all available enforcement mechanisms.
- Consider payment withholding requests.
- Act before they move assets or go broke.
12. Protect yourself for next time
- Learn from the experience.
- Tighten up your systems.
- Consider different contract terms.
- May need to reconsider working with that client.
Common Mistakes That Cost Builders Money
We see these mistakes all the time. Don't make them:
Mistake #1: Not Calling Payment Claims "Payment Claims"
If you don't explicitly state it's a payment claim under the BIF Act, you might not be able to use the Act's enforcement tools. Always include the magic words.
Mistake #2: Missing Deadlines
The BIF Act is full of strict deadlines. Miss them and you lose rights. Set up systems to track:
- When you can issue payment claims.
- 15 business day deadline for payment schedules.
- Deadlines for adjudication applications.
- 5 business day payment deadline after adjudication.
Mistake #3: Inadequate Payment Claims
Vague claims get disputed. Include:
- Detailed descriptions of work.
- Clear calculations.
- Supporting evidence.
- All the formal requirements.
Mistake #4: Not Keeping Records
You can't prove your claim without evidence. Document everything as you go.
Mistake #5: Waiting Too Long
Don't let debts pile up. The longer you wait:
- The harder it is to recover.
- The more likely the debtor becomes insolvent.
- The greater the impact on your cash flow.
Mistake #6: Accepting Unfair Contract Terms
Some contracts include terms that, while not completely void, make it harder to get paid:
- Very short deadlines for payment claims.
- Onerous dispute resolution procedures.
- Excessive retention amounts.
Get contracts reviewed before signing.
Mistake #7: Continuing Work When Not Being Paid
If they're not paying, why keep going? You have the right to suspend work. Use it.
Mistake #8: DIY Adjudication
Adjudication applications are complex legal documents. One mistake can cost you tens or hundreds of thousands of dollars. Get professional help.
Mistake #9: Not Following Up on Wins
Winning an adjudication is great, but you still need to enforce it if they don't pay. Have an enforcement plan ready.
Contact Odyssey Legal
Phone: (07) 5370 8759
Email: info@odysseylegal.com.au
Website: www.odysseylegal.com.au
Office Hours: Monday to Friday, 8:30am - 5:00pm
Ready to Get Paid?
Don't let unpaid invoices threaten your business. Contact Odyssey Legal today and let us help you recover what you're owed.
Book your free consultation now: [Click here]
Frequently Asked Questions
Can a head contractor just ignore my payment claim?
No. If they don't respond with a payment schedule within 15 business days (or any shorter contractual deadline), they become automatically liable to pay your full claimed amount. You can then apply for adjudication or sue them in court, and they can't raise any defense or reasons for withholding payment.
What if my contract says I have to go to arbitration or mediation first?
The BIF Act overrides contract terms that try to delay or prevent payment claims. You don't have to go through other dispute resolution processes before claiming payment or applying for adjudication. Section 200 makes any provisions that try to exclude or modify the BIF Act 's operation void.
Can I claim for variations even if they're not approved in writing?
You can claim for any work you actually performed under the contract, including variations. However, it's much easier to succeed if you have written approval. Without it, you'll need strong evidence that:
- The variation was requested or approved.
- You actually did the work.
- The work was necessary or beneficial.
- The value is reasonable.
This is one reason why getting written approval for variations before doing the work is so important.
My contract has a "pay when paid" clause. Does that mean I have to wait?
Generally, no. Section 74 of the Act makes "pay when paid" clauses void, except in very limited circumstances; primarily where the party who's supposed to pay you is insolvent. You're entitled to payment based on the work you've done, not based on whether someone else has been paid.
What interest can I claim on late payments?
You're entitled to claim interest on overdue amounts at whichever rate is higher:
- The rate under the Civil Proceedings Act 2011; or
- The amount stipulated within the building contract.
Interest accrues from when payment was due until it's paid.
Can I suspend work if I'm not being paid?
Yes! Section 98 (in addition to your contract) gives you the right to suspend work if:
- You've served a payment claim
- The due date has passed
- You haven't been paid what you're owed
You must give at least 2 business days written notice before suspending. Once you suspend, you're protected from liability for any loss or damage the other party suffers because of the suspension.
What if I need the money urgently and can't wait for adjudication?
Adjudication is already the fastest option; typically 2-3 weeks for a decision. However, if you need funds immediately:
- Consider invoice financing or factoring.
- Talk to your bank about bridging finance.
- In extreme cases, you might be able to negotiate a partial payment to keep working while adjudication proceeds.
At Odyssey Legal, we can often expedite the process and help you explore all options.
Can adjudication decisions be challenged or overturned?
Adjudication decisions are meant to be final and binding (at least temporarily). They can only be challenged in Court in very limited circumstances:
- Jurisdictional error (the adjudicator didn't have the legal power to decide).
- Denial of natural justice (serious procedural unfairness).
- Fraud.
- Apprehended bias.
Courts take a very narrow view of what qualifies. The policy is that adjudication provides fast, interim cash flow while parties can still fight about the final position in court or arbitration later.
What if the other party goes broke before I get paid?
This is a real risk in construction. Strategies to protect yourself:
- Before it happens: Get security (bank or director guarantees, retention bonds) where possible; claim regularly to minimise exposure; watch for warning signs.
- If it happens: Act immediately; consider payment withholding requests to go after higher parties; lodge a proof of debt in their insolvency; register your adjudication decision as a judgment; consider directors' personal liability (in some cases).
Time is critical when insolvency hits. Get legal advice immediately.
Do I need a QBCC license to use the Act?
If you're required to hold a QBCC license for the work you're claiming payment for, you must hold the appropriate license. Adjudicators will reject claims for unlicensed work because they have no jurisdiction to determine progress payments for work that shouldn't have been legally performed.
Always ensure you're properly licensed before starting work.
Can I make multiple payment claims for the same reference date?
No. You can only make one payment claim per reference date. If you issue multiple claims for the same reference date, only the first valid claim counts. If you miss something in your first claim, you generally can't claim it again for the same reference date—you'll need to wait for the next reference date.
This is why it's important to be thorough when preparing payment claims.
What happens if we settle the dispute after I've applied for adjudication?
You can withdraw your adjudication application at any time before the adjudicator makes a decision. Section 97 sets out the withdrawal process. If you withdraw:
- You may need to pay some of the adjudicator's fees.
- The adjudicator won't make a decision.
- You preserve the ability to apply for adjudication again (within the original deadlines) if the settlement falls through.
Get any settlement in writing and ensure payment is made before formally withdrawing.
How do payment withholding requests work with trust accounts?
If the head contractor is required to use a project trust account under the Act's trust provisions, payment withholding requests interact with trust requirements. The head contractor must still deposit amounts into the project trust account but must then hold the required amount for payment to you instead of paying it to your contractor.
This area can be complex, so get legal advice if you're dealing with both trust accounts and payment withholding requests.
Can I use the Act for maintenance contracts or ongoing work?
Yes, the Act applies to construction contracts including maintenance contracts, provided the work qualifies as "construction work" under the Act's broad definition. You can make payment claims at regular intervals for ongoing maintenance work.
What if I'm a sole trader or working under an ABN—am I covered?
Yes, as long as you're genuinely an independent contractor (not an employee), you're covered by the Act. It doesn't matter if you're a sole trader, partnership, or company. The key distinction is that the Act doesn't apply to employment relationships; you need to be working under a contract for services, not a contract of service.
Take Action Now: Don't Leave Money on the Table
Every day you wait is another day without the money you're owed. If you're facing payment problems:
Call Odyssey Legal Today
We offer builders and trades:
✓Complimentary Initial Assessment
- Quick review of your situation.
- Clear guidance on your options.
- No-obligation discussion.
✓ Adjudication Services
- Full preparation of adjudication applications.
- Expert representation throughout the process.
✓ Rapid Response
- We understand deadlines are tight.
- Same-day response for urgent matters.
- Efficient, focused service.
✓ Results-Focused Approach
- We've recovered numerous amounts for builders and trades.
- Strategic advice to maximise your recovery.
- Aggressive when needed, pragmatic always.
Don't Wait Until It's Too Late
Payment problems rarely fix themselves. The sooner you act:
- The more options you have.
- The more likely you are to get paid.
- The less damage to your cash flow.
Missing a deadline can cost you everything. Let us make sure that doesn't happen.