Critical Lessons from Recent Construction Disputes
Seven Critical Lessons from Recent Construction Disputes: What Queensland Builders Need to Know
Published by Odyssey Legal | Business, Construction & Litigation Lawyers
The construction industry faces constant legal challenges. From payment disputes to expert evidence failures, recent cases reveal costly mistakes that Queensland builders and contractors continue to make. Understanding these issues isn't just about avoiding litigation - it's about protecting your business, your reputation and your bottom line.
Drawing on recent decisions and industry developments, here are seven critical lessons every Queensland builder should understand.
1. Payment Disputes: You Cannot Extend Security of Payment Deadlines
The Issue: Many standard construction contracts include clauses that deem notices sent after 5pm to be received the next business day. Builders often rely on these clauses to extend their time to respond to payment claims.
The Reality: These deeming clauses are void when they conflict with the Building Industry Fairness (Security of Payment) Act 2017 (Qld).
In the New South Wales case Sharvain Facades Pty Ltd v Roberts Co (NSW) Pty Ltd, a contractor sent a payment claim via electronic messaging at 7:17pm on a Friday. The principal argued that under the contract's deeming clause, the claim was not received until 9am Monday, giving them until the following week to respond with a payment schedule.
Both the trial Court and Court of Appeal rejected this argument. The Courts confirmed that whilst parties can contractually shorten the timeframe for responding to payment claims, they cannot extend it. The policy behind security of payment legislation is to facilitate prompt payment and quick resolutions. Allowing parties to defer statutory deadlines would undermine this purpose.
What This Means for You:
If you receive a payment claim after 5pm, your statutory deadline to respond begins immediately; not the next business day. Don't rely on deeming clauses in your contract to extend security of payment timeframes. Missing the deadline means you'll be liable to pay the full claimed amount, regardless of whether the claim has merit.
Action Steps:
- Review your contracts with a construction lawyer to understand which clauses may be void under Queensland's security of payment legislation.
- Implement systems to monitor payment claims received electronically outside business hours.
- Train your administration team on the strict statutory deadlines that apply to payment schedules.
- When in doubt, respond within the shortest possible timeframe.
2. Expert Evidence: The Danger of Failing to Consider Alternative Rectification Options
The Case: In 85 Princess Pty Ltd v Fleming, a property owner discovered serious cracking in a concrete slab that supported two warehouses. The owner's expert recommended complete removal and replacement at a cost of over $5.3 million.
The builder's expert proposed a different approach: monitor the cracks and repair them as needed using epoxy or polymer resin - a significantly less expensive solution.
The Court's Decision: The court found the builder had breached contractual warranties regarding the slab construction. However, the court awarded only nominal damages of $100.
Why? Because whilst the owner proved the builder's breach, they failed to prove their loss. The owner led no evidence about the cost of the alternative monitoring and repair approach. The court found that:
- The owner's interest was commercial, not personal.
- A monitoring and repair strategy would adequately protect that commercial interest.
- Awarding $5.3 million would give the owner a windfall when a much cheaper solution existed.
- It would not be reasonable or rational for the owner to actually spend $5.3 million on complete replacement.
What This Means for You:
When defending defect claims, always obtain expert evidence about alternative rectification methods. If you can demonstrate a reasonable, less expensive repair option exists, the claimant must prove why the more expensive option is necessary - and what the cheaper option would cost.
Action Steps:
- Engage experts early who can identify practical, cost-effective rectification options.
- Don't just defend on the basis that no defect exists; also prepare evidence on proportionate repair costs.
- Keep detailed records of any interim repairs or monitoring you undertake.
- Consider making reasonable offers to rectify defects using proven, cost-effective methods.
3. Imported Fabricated Steelwork: A Growing Risk to Your Projects
The Problem: Some developers and contractors turn to offshore steel fabricators attracted by lower prices. However, this cost saving often comes with serious compliance failures, project delays and legal disputes.
The Australian Steel Institute's Technical Note TN018 outlines critical compliance issues with imported fabricated steelwork, including:
- Inadequate or falsified material certification.
- Non-compliant welding procedures and qualifications.
- Surface treatment failures leading to accelerated corrosion.
- Lack of traceability and documentation.
- "Compliance washing" where false claims are made about meeting Australian standards.
Real-World Examples:
Sydney Sound Barrier Truss: A 62-metre steel truss for a glass acoustic barrier was imported from Vietnam. The steel was 25% below specified yield strength. Welds cracked. Cross chords were filled with water (suspected fraud to meet shipping weight). The protective coating was non-compliant with rust evident before installation.
Initial cost difference between local and imported fabrication: $100,000. Rectification and rebuild costs: $810,000. The ultimate cost was borne by the engineer's professional indemnity insurance.
Kew Recreation Centre Roof Collapse: WorkSafe Victoria charged two companies following the collapse of imported structural steelwork. Investigations revealed failures in quality assurance processes for the imported steel truss.
What This Means for You:
All fabricated structural steelwork used in Australian projects, whether produced domestically or overseas, must comply with Australian Standards and the National Construction Code. Simply accepting overseas certifications is not enough.
Action Steps:
- Specify AS/NZS 5131 explicitly in all procurement and design documentation.
- Engage steelwork compliance consultants to perform supplier audits before fabrication begins.
- Ensure welding procedures and personnel are qualified to AS/NZS 1554.
- Require traceability and independent material certification for all steel batches.
- Use fabricators certified by Steelwork Compliance Australia (SCA) wherever possible.
- Develop a compliance management plan documenting all verification steps.
- If importing steel, arrange factory acceptance testing and inspections before shipment.
The cost of preventing a compliance failure is almost always less than the cost of rectifying one.
4. Arbitration Awards: The High Bar for Setting Them Aside
The Case: In Clarke Energy (Australia) Pty Ltd v Power Generation Corporation, a contractor lost an arbitration concerning extensions of time and variations on two power station projects. The contractor then applied to set aside the arbitration award, arguing the arbitrator failed to consider whether the principal acted "fairly and reasonably" in assessing extension of time claims.
The Court's Decision: The application was dismissed. The court found:
- The contractor never properly pleaded this issue in the arbitration.
- Even if the issue had been raised, the arbitrator did consider it.
- Setting aside an arbitral award requires proof of "real unfairness or real practical injustice"; not mere procedural imperfection.
- Courts will not use natural justice complaints as a backdoor to re-litigate factual findings from arbitrations.
The contractor was ordered to pay the principal's costs on an indemnity basis, a severe penalty reflecting the court's view that the application was "for all intents and purposes devoid of merit."
What This Means for You:
If your contract includes an arbitration clause, the arbitrator's decision will be final except in very limited circumstances. Don't assume you can challenge an unfavourable award by claiming procedural unfairness.
Action Steps:
- Take arbitration proceedings as seriously as court proceedings.
- Ensure all your arguments are properly pleaded in the arbitration.
- Don't rely on raising new legal arguments late in the process.
- If you identify an issue the arbitrator should consider, plead it clearly and early.
- Obtain legal advice before agreeing to arbitration clauses in contracts.
- Consider whether your dispute is better suited to court proceedings or alternative dispute resolution.
5. Principal's Right to Set-Off: Contract Amendments Can Remove This Right
The Case: In Pacific Diamond 88 Pty Ltd v Tomkins Commercial & Industrial Builders Pty Ltd, a building contract was based on the AS4902-2000 standard form but with amendments.
During negotiations, the contractor requested that the principal should not be able to deduct liquidated damages from certified progress payments. The final executed contract included amendments that:
- Required the superintendent to certify liquidated damages before the principal could recover them.
- Deleted the clause that allowed the superintendent to set off retention monies against progress payments.
Despite this deletion, other parts of the clause still referred to the deleted paragraph as if it existed.
The Court's Decision: The Queensland Court of Appeal found that:
- The deletions showed the parties had rejected the mechanism allowing set-offs against progress payments.
- These deletions were not just evidence of prior intent; they showed what was "rejected by both parties".
- The principal could only set off certified liquidated damages at final payment, not against progress claims.
- However, the right to set off at final accounting remained.
What This Means for You:
Standard form contracts like AS4902 are often amended during negotiations. These amendments can fundamentally change your rights, including your ability to set off liquidated damages or other amounts against progress payments.
Action Steps:
- Never assume a standard form contract operates as intended if clauses have been deleted or amended.
- Have a construction lawyer review all contract amendments before execution.
- Pay particular attention to deletions that affect payment, set-off rights and dispute resolution.
- If negotiating contracts, understand that requesting removal of clauses may have unintended consequences.
- Keep detailed records of pre-contractual negotiations about contract terms.
- Don't rely on your "usual understanding" of how standard form contracts work.
6. Owners Corporation Disputes: Jurisdiction Matters More Than You Think
The Issue: For years, owners corporations in Victoria routinely pursued unpaid levies against lot owners in the Magistrates' Court. This changed dramatically in 2024.
The Cases: In a series of decisions (Owners Corporation v Buckley, Jones, Miller and Nguyen), the Magistrates' Court of Victoria clarified that VCAT - not the Magistrates' Court - has exclusive jurisdiction over owners corporations' fee recovery claims against lot owners.
The court found that sections 30(2) and Division 1 of Part 11 of the Owners Corporations Act 2006 (Vic) create an implied ouster of the Magistrates' Court jurisdiction for these specific disputes.
What This Means for Queensland Builders:
Whilst these are Victorian cases, they illustrate an important principle: don't assume you can choose which court or tribunal to file in. Statutory schemes often designate exclusive jurisdiction to particular bodies.
In Queensland, the Queensland Civil and Administrative Tribunal (QCAT) has jurisdiction over many building disputes. Understanding which disputes must go to QCAT, which can go to court, and which offer a choice is critical.
Action Steps:
- Before commencing any proceedings, obtain legal advice on the correct jurisdiction.
- Don't "forum shop" by filing where you think you'll get a better outcome.
- Filing in the wrong jurisdiction wastes time and money, and may result in cost orders against you.
- If someone files against you in the wrong jurisdiction, raise this issue immediately.
- Review your dispute resolution clauses to ensure they don't inadvertently require proceedings in a forum that lacks jurisdiction.
7. Expert Evidence in Building Disputes: New Approaches in Victoria (and What Queensland Can Learn)
The Development: In Victoria's County Court Commercial Division, there's been a significant shift towards appointing single joint experts rather than allowing each party to appoint their own expert.
Between August 2022 and January 2025, in the Building Cases List, 23% of matters involved single joint expert appointments, with 77% still using party-appointed experts.
The Rationale: Single joint experts can:
- Reduce bias and partisanship.
- Narrow the issues in genuine dispute.
- Shorten trials (by an average of 2-3 days).
- Enable faster judgment delivery (saving approximately 3 months).
- Encourage earlier settlement.
- Reduce overall costs.
When Single Joint Experts Work Best:
- Discrete, single-issue questions (waterproofing defects, materials verification, valuations).
- Lower-value disputes.
- Matters where there's a clear methodology.
When Party-Appointed Experts Remain Appropriate:
- Complex, multi-issue disputes.
- Cases involving competing methodologies.
- Matters where reasonable expert opinions may legitimately differ.
- High-value claims where detailed contradictory evidence is necessary.
What This Means for Queensland Builders:
Whilst Queensland has not adopted the same default position as Victoria, QCAT and Queensland courts increasingly encourage expert collaboration through joint reports and conferences.
Action Steps:
- Consider proposing a single joint expert for discrete technical issues in your disputes.
- If experts are appointed by each party, ensure they participate constructively in conferences.
- Brief your expert on their paramount duty to the tribunal or court - not to you.
- Don't instruct experts to "advocate" for your position.
- Ensure expert reports comply with the expert witness code of conduct.
- Never attempt to draft or substantially amend an expert's report yourself.
- Keep instructions to experts transparent and be prepared to disclose them if required.
The Broader Message: Proactive Risk Management
These seven lessons share a common thread: proactive risk management prevents expensive reactive disputes.
Key Principles:
- Understand Your Contract: Don't assume standard terms apply if amendments have been made. Have contracts reviewed by a construction lawyer before signing.
- Know Your Statutory Rights and Obligations: Security of payment legislation, building legislation and industry-specific laws often override contractual terms. Understand what you can and cannot contract out of.
- Document Everything: From payment claims to defect notices to expert instructions, thorough documentation protects you if disputes arise.
- Engage Experts Appropriately: Recognise experts' duties to the court or tribunal. Don't treat them as advocates. Ensure they consider all reasonable options, not just the option that best suits your case.
- Consider Alternatives: Whether it's alternative rectification methods, alternative dispute resolution, or alternative business strategies, flexibility often leads to better commercial outcomes than rigid "all or nothing" positions.
- Act Quickly on Statutory Deadlines: Security of payment deadlines cannot be extended by contract. Missing them has severe consequences.
- Verify Compliance: Especially with imported materials and specialist work, don't accept overseas certifications at face value. Verify compliance with Australian standards before problems arise.
When to Seek Legal Advice
Don't wait until you're in litigation to seek legal advice. Obtain guidance:
- Before signing construction contracts, particularly if they're amended standard forms.
- When you receive payment claims, especially late in the day or before weekends.
- Before responding to defect notices or warranty claims.
- When considering importing materials or engaging overseas suppliers.
- Before commencing dispute resolution proceedings.
- When served with proceedings, arbitration notices or QCAT applications.
- Before instructing experts or responding to expert evidence.
Conclusion
The construction industry operates in a complex legal environment. Recent cases demonstrate that assumptions based on "how things have always been done" can be costly. Security of payment deadlines cannot be extended. Standard contract terms may be amended in ways that fundamentally change your rights. Jurisdiction matters. Expert evidence requires careful management.
The good news? Most of these problems are preventable through proper legal advice, robust contract management and proactive compliance systems.
Understanding these seven lessons won't just help you avoid disputes - it will help you run a more profitable, more efficient and more sustainable construction business.
Need advice on construction contracts, payment disputes or building litigation? Odyssey Legal has extensive experience advising Queensland builders and construction businesses on all aspects of construction law. Contact us to discuss how we can help protect your business.
Contact Odyssey Legal:
- Phone: 07 5370 8759
- Email: info@odysseylegal.com.au
- Location: Servicing all of Queensland
- Book Your Free Initial Consultation: We offer a free initial consultation to assess your situation and provide clear advice on the best path forward.
About Odyssey Legal
Odyssey Legal is an expert building & construction law firm, servicing all of Queensland. We focus on helping Queensland builders, contractors and trades, resolve disputes, recover debts, and protect their interests through strategic legal advice.
Frequently Asked Questions
Can I rely on a contract clause that says notices sent after 5pm are received the next business day for security of payment claims?
No. These "deeming clauses" are void when they conflict with Queensland's Building Industry Fairness (Security of Payment) Act 2017. Your statutory deadline to respond to a payment claim begins when you receive it - not the next business day. Missing the deadline means you'll be liable to pay the full claimed amount, regardless of the claim's merit.
If I'm sued for building defects, do I have to pay for the most expensive rectification option?
Not necessarily. Recent cases confirm that claimants must prove their rectification costs are reasonable. If you can demonstrate a less expensive repair method would adequately address the defect, the claimant must prove why the more expensive option is necessary. This is why engaging experts who can identify practical, cost-effective solutions is critical to your defence.
Are overseas steel certifications sufficient to prove compliance with Australian building standards?
No. All fabricated structural steelwork used in Australian construction projects must comply with Australian Standards and the National Construction Code, regardless of where it's manufactured. Overseas certifications are not automatically equivalent to Australian standards. You must verify compliance through independent testing and certification by recognised Australian authorities. The cost of rectifying non-compliant imported steel far exceeds any initial savings.
Can I challenge an arbitration decision if I think the arbitrator got it wrong?
Only in very limited circumstances. Courts will only set aside arbitral awards where there's been a serious breach of natural justice causing "real unfairness or real practical injustice" - not mere procedural imperfections or disagreement with factual findings. If your contract includes an arbitration clause, you must treat the arbitration as seriously as court proceedings and ensure all your arguments are properly pleaded from the outset.
If my standard form contract has been amended, does it still work the way I expect?
Not necessarily. Amendments to standard form contracts like AS4902 can fundamentally change your rights. For example, deleting clauses about set-off can remove your ability to deduct liquidated damages from progress payments, even if other parts of the contract still refer to those deleted clauses. Always have a construction lawyer review amended contracts before signing.
Which court or tribunal should I file my building dispute in?
This depends on the type of dispute and the relevant legislation. In Queensland, QCAT has jurisdiction over many building disputes, whilst some matters must go to the District or Supreme Court. Filing in the wrong jurisdiction wastes time and money and may result in cost orders against you. Always obtain legal advice on the correct jurisdiction before commencing proceedings.
Should I agree to a single joint expert or insist on appointing my own expert?
It depends on the nature of your dispute. Single joint experts work well for discrete, single-issue questions like material verification or straightforward defect assessments. For complex disputes involving multiple issues or competing methodologies, party-appointed experts may be more appropriate. However, courts and tribunals increasingly encourage expert collaboration through joint reports and conferences, regardless of the appointment method.
What's the most important thing I can do to avoid construction disputes?
Proactive risk management. This means: understanding your contracts before signing them (especially amendments to standard forms); knowing your statutory rights and obligations under security of payment and building legislation; documenting everything thoroughly; meeting all statutory deadlines; verifying compliance with Australian standards (especially for imported materials); and seeking legal advice early rather than waiting until you're in litigation.