Relevant BIFA Decisions: What Queensland Builders Need to Know

  • February 11, 2026

About the Author: Damon

Queensland Construction Industry BIFA court decisions Queensland

Relevant Court Decisions That Changed the BIFA Game: What Queensland Builders Need to Know

Published by Odyssey Legal | Business & Litigation Lawyers

In the past two years, Queensland courts have handed down several landmark decisions that fundamentally changed how the Building Industry Fairness (Security of Payment) Act 2017 (BIFA).

These aren't abstract legal principles buried in case reports. They're rulings that determine whether your payment claim is valid, whether your adjudication application will succeed, and whether you'll recover what you're owed.

If you're still operating based on how things worked three years ago, you're already behind. Here's what the recent cases mean for your construction business and why understanding them could save you hundreds of thousands of dollars.

MWB EVERTON PARK v DEVCON BUILDING: THE INVOICE REQUIREMENT

In June 2024, the Queensland Court of Appeal delivered a decision in MWB Everton Park Pty Ltd v Devcon Building Co Pty Ltd [2024] QCA 94 that sent shockwaves through the construction industry.

The core issue was simple: what makes a valid payment claim under Section 68 of the BIFA Act?

Devcon had submitted what it called a "progress claim" for work completed. The document identified the work, stated the amount claimed, and provided all the details you'd expect. But it didn't use the word "invoice" and didn't explicitly request payment in clear terms.

The Court of Appeal ruled the payment claim was invalid.

Justice Mullins emphasised that all elements of Section 68 must be present with precision. A payment claim must actually request payment. Simply labelling a document a "progress claim" isn't enough under the BIFA Act. The document needs to use language like "invoice" or clearly state "payment is requested" or similar explicit wording.

This decision raised the bar significantly. Payment claims that would have been accepted as valid two years ago are now potentially invalid if they don't include clear payment request language.

What this means for your business: Review every payment claim you issue. Make sure you're using the word "invoice" prominently. Don't rely on implied requests for payment. Be explicit. One word can determine whether your claim is valid or worthless.

JOHN HOLLAND v SECUREFENCE: ADJUDICATOR ERROR AND ENFORCEMENT

In December 2024, the Supreme Court decision in John Holland Queensland Pty Ltd v SecureFence Pty Ltd [2024] QSC 290 demonstrated the consequences of adjudicator jurisdictional error.

SecureFence had won an adjudication for $187,270. The adjudicator had based the decision partly on an estoppel argument related to a document that wasn't actually part of the contract between the parties. The Supreme Court found this was jurisdictional error. The adjudicator had relied on something outside the contract when making the determination.

The court ordered SecureFence to repay $241,957.39 to John Holland.

This case illustrates two critical points. First, adjudicators must strictly comply with Section 88 of the BIFA Act, which limits what they can consider. Second, even if you win an adjudication, if the decision contains jurisdictional error, you may be ordered to repay everything, plus interest.

What this means for your business: Winning an adjudication isn't the end of the story. The other party can challenge the decision in the Supreme Court on jurisdictional grounds. If you've received an adjudicated amount, be prepared for the possibility that the respondent might succeed in having it set aside. Don't immediately spend money you've received from adjudication until you're certain the decision will stand.

CIVIL CONTRACTORS v GALAXY DEVELOPMENTS: LATE DECISIONS ARE VOID

The 2021 Court of Appeal decision in Civil Contractors (Qld) Pty Ltd v Galaxy Developments Pty Ltd [2021] QCA 10 established a principle that remains critically important: if an adjudicator makes a late determination in Queensland, the determination is void.

This differs from other states like New South Wales, where late determinations are still valid.

In Queensland, the adjudicator must make the decision within the statutory timeframe (10 business days for standard claims, 15 for complex claims). If they're even one day late, the entire determination is void.

The Court of Appeal went further in later cases to clarify that not only must the decision be made on time, but the determination must also be provided or notified as available within that timeframe. However, there's a silver lining: if a determination is void because it's late, the claimant has 5 business days to reapply for adjudication.

What this means for your business: Track the adjudicator's decision deadline carefully. If you're a respondent and the decision comes late, you may have grounds to challenge it as void. If you're a claimant and receive a late decision, act immediately to reapply within 5 business days. Don't assume a late decision is still binding.

Taringa Property Group v Kenik: Insolvency and Enforcement

The Supreme Court decision in Taringa Property Group Pty Ltd v Kenik Pty Ltd [2024] QSC 327 broke new ground on when courts will prevent enforcement of adjudication determinations.

Kenik won an adjudication for $4.2 million against Taringa. However, the court granted a stay preventing enforcement because Kenik was in precarious financial condition, and there was a very high risk they couldn't repay Taringa if Taringa later succeeded in substantive proceedings. In February 2025, Kenik was wound up, proving the court's concerns were well-founded.

What this means for your business: If you're a respondent facing a large adjudication loss against a financially unstable claimant, their financial position is relevant. Conversely, if you're a claimant in financial difficulty, the respondent may use this to prevent enforcement even after you've won.

BARRETT GROUP v KENIK: INSOLVENCY CONSEQUENCES

Following the Taringa decision, Barrett Group Pty Ltd v Kenik Pty Ltd [2025] QSC 25 in early 2025 showed what happens when the fears come true.

Kenik was wound up on 20 February 2025, demonstrating the real-world consequences when contractors in unstable financial positions can't enforce adjudication decisions.

What this means for your business: The interaction between adjudication and insolvency is complex and dangerous. If you're pursuing adjudication against a financially unstable party, be prepared for enforcement challenges. If you're in financial difficulty yourself and trying to enforce an adjudication, expect the respondent to raise your financial position as grounds for a stay.

Subcontractor Charges: A Stable and Reliable Framework

Unlike adjudication law, there haven't been major recent court decisions changing how subcontractor charges operate. The mechanism continues to function as set out in Chapter 4 of the BIFA Act, and this stability is itself significant.

The key requirements remain well-established: serve the notice of claim within three months of practical completion, obtain certification from a qualified person, serve both the principal and head contractor, and commence court proceedings within one month for standard claims.

Subcontractors with valid charges continue to become secured creditors under Section 471C of the Corporations Act 2001, giving them priority over unsecured creditors in a liquidation.

What this means for your business: Subcontractor charges remain a predictable and reliable protection tool. While adjudication law continues to evolve, the charge mechanism is stable and effective when used correctly.

The Clear Trend: Stricter Compliance

Looking across all recent cases, one trend is unmistakable: Queensland courts are becoming increasingly strict about BIFA Act compliance.

MWB v Devcon shows courts scrutinising payment claims more closely. John Holland v SecureFence shows courts setting aside adjudications for jurisdictional error. The late decision cases show courts enforcing timeframes with absolute strictness.

The days of rough-and-ready payment claims are over. Small errors that might have been overlooked a few years ago are now grounds for invalidity. You need to comply with every requirement, meet every deadline, and include every piece of information exactly as the statute requires.

Staying Ahead of Changing Construction Law

Construction law doesn't stand still. Cases like MWB v Devcon change the rules overnight. Practices that worked for years can suddenly stop working.

The businesses that succeed are those that adapt quickly. They update their payment claim templates. They track adjudicator deadlines. They understand when financial stability affects enforcement.

The message from recent Queensland case law is clear: precision matters. Compliance matters. Understanding the latest decisions matters. Because in Queensland construction law, what worked last year might not work today.

Need assistance with a payment claim or adjudication? Contact Odyssey Legal for a confidential consultation. We act for Queensland builders, contractors, and subcontractors.

Contact Odyssey Legal:

About Odyssey Legal

Odyssey Legal is an expert building & construction law firm, servicing all of Queensland. We focus  on helping Queensland businesses or our clients resolve disputes, recover debts, and protect their interests through strategic legal advice.

Frequently Asked Questions

Does the MWB v Devcon decision mean my existing payment claims are invalid?

Not necessarily. If your payment claims used the word 'invoice' or clearly requested payment, they likely remain valid. If they only said 'progress claim' without requesting payment, they may be challenged. Review your templates immediately.

What should I do if I receive a late adjudication decision?

First, confirm it's actually late by calculating the deadline in business days. If it is late, the decision is void in Queensland. As a claimant, you have 5 business days to reapply. As a respondent, you can refuse to pay.

Can I still enforce an adjudication decision if my business is in financial difficulty?

Possibly, but the respondent may seek a stay of enforcement on the grounds you couldn't repay the money if they later succeed in court. The court will assess the risk based on your financial position, as demonstrated in Taringa Property Group v Kenik.

Are subcontractor charges affected by recent case law changes?

No. Subcontractor charges continue to operate under the stable framework of Chapter 4 of the BIFA Act. The procedures and requirements haven't changed through recent court decisions.

How often should I review my BIFA Act procedures?

At minimum, annually. For significant decisions like MWB v Devcon, update procedures immediately. Consider subscribing to construction law updates or engaging a construction lawyer to keep you informed.

What is the most important lesson from recent BIFA Act case law?

Courts are becoming stricter about compliance. Every requirement must be met exactly. Every deadline must be met precisely. There's no room for approximation or close enough anymore.

If an adjudicator makes a jurisdictional error, can I get the decision set aside?

You can apply to the Supreme Court, but it's not guaranteed. You'll need to establish genuine jurisdictional error and act quickly. Seek legal advice immediately if you believe a decision contains jurisdictional error.

About the Author: Damon

Damon Laffin is the Director of Odyssey Legal, with extensive experience in commercial litigation, dispute resolution, defamation, insolvency, and debt recovery. He works closely with individuals and businesses to deliver practical, strategic legal advice, helping clients resolve complex legal matters with confidence.

Connect with Damon on Linkedin

Free initial consultation

Book Your Free Initial Consultation

We offer a free initial consultation to assess your situation and provide clear advice on the best path forward.

  • 07 5370 8759

  • Servicing all of Queensland

  • info@odysseylegal.com.au