When Owners Claim for Stress and Disappointment


What Queensland Builders Need to Know
When a building dispute escalates to litigation, the standard heads of damage are familiar: defect rectification costs, delay damages, variations in dispute. But owners increasingly add another line to their claims: damages for distress, inconvenience or disappointment. Sometimes described as solatium or consolation damages, sometimes framed as loss of amenity, these claims attempt to put a dollar figure on the emotional and physical toll of a project gone wrong.
For builders and contractors facing a cross-claim that includes these heads of damage, understanding the legal limits is essential. The law draws a tight boundary around when these damages are recoverable, and that boundary works largely in your favour.
The Edwards case is the most thoroughly litigated Queensland building dispute on this subject. The same dispute was considered by QCAT at first instance, then the QCAT Appeal Tribunal in Edwards v Sovereign Homes (QLD) Pty Ltd [2020] QCATA 146, and finally by the Queensland Court of Appeal in Edwards v Sovereign Homes Qld Pty Ltd [2022] QCA 4. The owner lost at every level. The reasons why are instructive for builders across the state.
This article explains the full litigation history, the legal framework governing distress and inconvenience claims, and what builders should understand when facing these claims.
The Edwards Case: Three Proceedings, One Outcome
The Facts
Sovereign Homes Qld Pty Ltd was engaged under a standard HIA Queensland Plain Language Alteration, Addition and Renovation Contract (QC3 form) to construct an extension to a residential property in Fairfield, Brisbane. The works involved adding a fourth level with three bedrooms, a bathroom, a separate toilet and a retreat.
Before practical completion, the completed works were damaged by heavy rain in August 2014 and, more substantially, by a hailstorm in November 2014. Sovereign made insurance claims in respect of both events. On 11 December 2014, Sovereign delivered a 'Certificate on Practical Completion' and its final claim of $46,155.20. At that time, weather event damage to the works remained unrepaired. Sovereign contended it was willing to repair the damage but the owner refused access to the site.
The owner disputed practical completion, refused to pay the final claim, and made a cross-claim of over $133,000. That cross-claim included the cost of rectifying weather damage, delay damages, and a claim for consolation damages (solatium) and loss of amenity.
QCAT at First Instance: Sovereign Succeeds against loss of amenity claim
The QCAT member found that practical completion had been achieved on 11 December 2014. Critically, the owner had signed the Certificate on Practical Completion at a site meeting, had told the builder's project manager he would forward the bank transfer that evening, and had sent a text message the following day confirming he was happy to sign. The member found the owner was satisfied practical completion had been reached and that the weather damage was a separate issue.
The member ordered the owner to pay Sovereign's final claim of $46,155.20 plus interest, but also ordered Sovereign to pay the owner $79,938.30 (covering rain damage, hail damage and other defects) plus interest. The owner was ordered to pay 70 per cent of Sovereign's costs. The solatium and loss of amenity claims were rejected.
QCATA: The Appeal Tribunal Dismisses the Appeal
The owner sought leave to appeal on numerous grounds, including errors of law relating to practical completion, the weather damage works, and the rejection of distress damages. The QCATA Appeal Tribunal refused leave and dismissed the appeal.
On the distress damages question, the Appeal Tribunal confirmed that:
- damages for loss of amenity were not recoverable in these circumstances;
- damages for non-physical inconvenience and distress were only recoverable where they were consequent upon real and substantial physical inconvenience caused by the breach; and
- the owner had not discharged the onus of proof on that question.
| Edwards v Sovereign Homes (QLD) Pty Ltd [2020] QCATA 146
An owner's claims for solatium and loss of amenity in a domestic building dispute were rejected. Non-physical distress and inconvenience are recoverable only where caused by real and substantial physical inconvenience. The claimant carries the burden of proof on that question. |
The Court of Appeal: The Final Chapter
The owner then applied to the Queensland Court of Appeal (Fraser and McMurdo JJA and Davis J) for leave to appeal from the QCATA decision, confining the application to a single ground: whether the tribunal member erred in law in finding that a separate contract or scope of works was required for the weather-damaged works and that practical completion was achieved before those works were rectified.
The distress and solatium damages ground was not pursued in the Court of Appeal. The QCA application focused entirely on the practical completion and weather damage construction question.
The Court of Appeal dismissed the application for leave. Fraser JA (with McMurdo JA and Davis J agreeing) reached this conclusion for two principal reasons.
First, on the construction question itself, the Court held that although it was reasonably arguable that the scope of the contractor's works under clause 1 comprehended the repair of damage to works incurred before practical completion, the owner had an insurmountable problem: the tribunal member had found, unchallenged, that the owner had already taken possession of the works at the time of the 11 December 2014 meeting and was aware that Sovereign would attend to the weather damage works once its insurance claim was settled. The clause 24.9 deeming mechanism was decisive.
Clause 24.9 of the HIA QC3 contract provides that the date stated in the builder's notice of practical completion is deemed to be the date of practical completion unless, within five working days of receiving that notice, the owner gives written notice disputing the date and detailing the reasons for the dispute. The owner did not issue that notice within five working days. The Court held that this deeming mechanism operated to fix the date of practical completion regardless of whether the construction question was resolved in the owner's favour.
Second, and practically significant, the Court found that even if the owner succeeded on the construction point, the financial benefit of doing so was marginal when measured against the costs of the proposed appeal. If the owner won, the net outcome on remitter would likely be a net order in his favour of $33,783.10 (being $79,938.30 minus $46,155.20), rather than the tribunal member's outcome of orders 1 and 2 operating against each other. That net benefit did not justify the cost of the appeal.
| Edwards v Sovereign Homes Qld Pty Ltd [2022] QCA 4
The Queensland Court of Appeal refused leave to appeal. The clause 24.9 deeming provision operated to fix the date of practical completion where the owner failed to give a written dispute notice within five working days. The practical completion dispute could not be revived on appeal even if the construction argument had merit. The application was dismissed with costs. |
The Three Critical Lessons from the Edwards Case
Lesson 1: Distress and Solatium Claims Have a High Evidentiary Bar
The rejection of the solatium and loss of amenity claims at QCAT and QCATA was never revisited before the Court of Appeal. That is significant. After three proceedings and eight years of litigation, those claims failed entirely. The reason was not that distress claims can never succeed in building disputes, but that the owner could not establish the legal prerequisites.
Australian contract law does not generally permit recovery for mental distress or disappointment in breach of contract claims. The foundational principle, traced from Addis v Gramophone Co Ltd [1909] AC 408 through to the High Court's decision in Baltic Shipping Co v Dillon (1993) 176 CLR 344, is that these claims are only available where either:
- the very object of the contract was to provide pleasure, relaxation or peace of mind (the 'pleasure object' category, which does not include building contracts); or
- the breach caused real and substantial physical inconvenience from which mental distress was a direct consequence.
The owner in Edwards could not bring the claim within either category on the evidence. His claim amounted to distress and disappointment at the building experience and the dispute itself. That is not sufficient.
| Baltic Shipping Co v Dillon (1993) 176 CLR 344
The High Court's authoritative statement: damages for disappointment and distress are recoverable only (a) where the object of the contract was to provide enjoyment or relaxation, or (b) where the distress proceeds from real and substantial physical inconvenience caused by the breach. Building contracts do not fall within category (a). |
| Moore v Scenic Tours Pty Ltd [2020] HCA 17
The High Court confirmed that the Baltic Shipping categories remain good law in Australia. Building contracts are not contracts to provide pleasure or relaxation. The physical inconvenience pathway remains the only avenue for building owners, and it requires real evidence of actual physical conditions caused by the breach. |
Lesson 2: The Clause 24.9 Deeming Mechanism Is a Powerful Protection for Builders
The Court of Appeal's analysis of the deeming provision in clause 24.9 of the HIA QC3 contract is of critical practical importance for Queensland builders using that form.
Clause 24.9 deems the date stated in the builder's notice of practical completion to be the date of practical completion unless the owner gives written notice within five working days disputing the date and detailing the reasons. The Court of Appeal held that this mechanism operated in the builder's favour in Edwards regardless of whether the owner's construction argument about the weather damage works had merit. Because the owner signed the Certificate on Practical Completion, indicated satisfaction that practical completion had been reached, and did not issue a timely written dispute notice, the deeming provision was triggered and the dispute was effectively foreclosed.
This has three direct implications for builders:
- Issue your practical completion notice in writing and in the correct form. The notice triggers the five-working-day clock. If the owner does not respond in time with a written notice disputing the date and giving reasons, the deeming provision operates in your favour.
- Document the practical completion meeting. In Edwards, the builder had a signed Certificate on Practical Completion, evidence of the owner's satisfaction expressed at the meeting, and subsequent text messages confirming agreement. That contemporaneous documentary record was decisive at every level of the litigation.
- Preserve the deeming provision outcome in your evidence. If an owner later disputes practical completion having not responded within five working days, your evidence of the notice, the meeting and the absence of a timely dispute will be the foundation of your defence.
| HIA QC3 Contract, Clause 24.9 (as applied in Edwards v Sovereign Homes [2022] QCA 4)
The date stated in the builder's last notice of practical completion is deemed the date of practical completion unless the owner gives written notice within five working days disputing the date and detailing the reasons. Failure to give that notice operates conclusively in the builder's favour. |
Lesson 3: The Weather Damage and Scope of Works Question Remains Open
Although the Court of Appeal refused leave, it did not hold that the owner's construction argument was wrong. Fraser JA expressly found it was reasonably arguable that the scope of the contractor's works under clause 1 of the HIA QC3 contract comprehended the repair of damage to works incurred before practical completion, where that damage resulted from an event for which the contractor was required to take out insurance and was entitled to an extension of time.
The question was not decided on its merits. It was refused because the deeming provision made it immaterial on the facts and the financial benefit of succeeding was marginal compared with the costs involved.
This leaves an open question for Queensland builders using HIA standard form contracts: what happens when works completed under the contract are damaged by weather or other insured events before practical completion, and the owner disputes that practical completion has been reached on that basis? The Court of Appeal's analysis suggests the answer may not be straightforward, and that clause 16 extension of time provisions and the insurance and risk allocation clauses in the contract may all bear on the answer.
| Open Question for Builders Using HIA QC3 Contracts
The Court of Appeal found it was reasonably arguable that weather event damage to completed works before practical completion may fall within the contractor's contractual scope of works under clause 1, read with the insurance and extension of time provisions. This question was not decided on its merits. Builders facing weather damage disputes before practical completion should seek legal advice on how the contract allocates that risk and what their entitlements and obligations are. |
The Legal Framework: Why Distress Claims Usually Fail in Building Disputes
The General Rule and Its Exceptions
Australian contract law begins from the position that damages for mental distress, disappointment or injured feelings are not recoverable for breach of contract. The burden is on the owner to bring themselves within one of the narrow recognised exceptions.
The two exceptions are the pleasure object category (which does not apply to building contracts) and the physical inconvenience category. For the physical inconvenience category, the English Court of Appeal in Watts v Morrow [1991] 1 WLR 1421 confirmed that where a breach causes real and substantial physical inconvenience, and mental distress is a direct consequence of that physical inconvenience, the distress may be compensable. But the foundational case of Hobbs v London and South Western Railway Co (1875) LR 10 QB 111 drew an express line:
| Hobbs v London and South Western Railway Co (1875) LR 10 QB 111
Mere annoyance, vexation, loss of temper or disappointment without physical dimension are not compensable. The inconvenience must be real, substantial, and productive of physical consequences. This foundational distinction continues to govern building dispute distress claims in Australia. |
| Archibald v Powlett [2017] VSCA 259
The Victorian Court of Appeal confirmed that distress and inconvenience damages in a contract dispute require actual disruption and physical imposition caused by the breach itself, not merely the time and trouble of dealing with the consequences of the breach. |
What an Owner Must Prove
When an owner makes a distress or inconvenience claim against a builder, they must establish each of the following:
- A proven breach of contract. Distress is a head of damages consequent on a breach. No breach means no claim.
- Real and substantial physical inconvenience caused by that breach. Not frustration with the process. Actual physical conditions with physical effects on how the owner lived.
- Particularised evidence. Contemporaneous diary records, photographs, medical evidence if health was affected. General assertions of stress will fail.
- The distress must be caused by the breach, not by the dispute, the litigation, or the owner's financial circumstances.
In Edwards, the owner failed to establish these elements. The experience of a deteriorating builder-owner relationship, a protracted dispute and resulting stress did not satisfy the physical inconvenience requirement.
Quantum: The Awards Are Modest Even When Claims Succeed
Even where a distress or inconvenience claim is properly established, the award is modest. English authorities (which Australian courts treat as persuasive) have placed the range for distress and inconvenience in building cases at a few thousand dollars per year of genuine physical exposure to the disruptive conditions. Courts consistently moderate these awards by recognising that the suffering, while real, is transient. The psyche is not permanently impaired and the claimant gets on with life.
Practical Implications for Queensland Builders
On Distress and Solatium Claims
When a cross-claim includes a solatium or distress component, ask:
- Does the claim particularise physical inconvenience specifically caused by the alleged breach, or is it a general assertion of stress and upset?
- Can the owner produce contemporaneous evidence of the physical conditions they claim to have endured?
- Was the owner actually living in or around the property during the relevant period?
- Is the claimed distress connected to the breach, or to the dispute process itself?
Where the evidence does not exist to support the physical inconvenience threshold, the realistic legal exposure on a distress or solatium component is low. Do not settle these claims at face value.
On Practical Completion Documentation
The Court of Appeal outcome in Edwards underlines how critical it is to get practical completion documentation right. For every project using HIA QC3 or similar standard form contracts:
- issue a written notice of practical completion in the contractually required form;
- conduct the practical completion inspection properly and document what was observed;
- obtain the owner's signed acknowledgment of practical completion if possible;
- note any defects agreed to be minor in writing, with completion timeframes;
- follow up in writing if the owner raises questions at the meeting; and
- retain all text messages, emails and communications around the practical completion date.
If the owner does not issue a written notice of dispute within five working days of your notice of practical completion, the deeming provision is triggered. Your contemporaneous records will be the evidence that proves the notice was given and no timely dispute was received.
On Weather Damage Before Practical Completion
The Court of Appeal left open the question of whether damage to completed works caused by weather events before practical completion falls within the contractor's contractual scope. If you face this situation, the HIA QC3 contract provisions on insurance, risk allocation and extensions of time all interact. Given the uncertainty highlighted by the Edwards litigation, legal advice before taking a position on whether weather damage works require a separate agreement is prudent.
Understand the Cost-Benefit of Litigation
One of the most striking aspects of the Court of Appeal's decision in Edwards is the frank assessment that even if the owner had won on the construction question, the financial benefit to him was likely less than $33,783. The costs of the Court of Appeal application, combined with the costs of any remitted proceeding, would have consumed a significant part of that sum. Fraser JA declined to grant leave in part on this basis.
For builders deciding whether to defend a cross-claim aggressively or to consider settlement, the same analysis applies in reverse. Understanding the realistic value of what the owner can actually recover, after netting off what you are owed under the contract, is essential to making sensible commercial decisions.
Contact Odyssey Legal
Contact Odyssey Legal:
- Phone: 07 5370 8759
- Email: info@odysseylegal.com.au
- Location: Servicing all of Queensland
- Book Your Free Initial Consultation: We offer a free initial consultation to assess your situation and provide clear advice on the best path forward.
About Odyssey Legal
Odyssey Legal is an expert building & construction law firm, servicing all of Queensland. We focus on helping Queensland businesses or our clients resolve disputes, recover debts, and protect their interests through strategic legal advice.
Frequently Asked Questions
Q. Can an owner claim damages for stress and distress caused by a building dispute?
A. Generally, no. Australian contract law does not permit recovery for mental distress, disappointment or injured feelings as a general head of damage for breach of contract. The rule traces back to Addis v Gramophone Co Ltd [1909] and has been confirmed consistently across Australian courts, including by the High Court in Baltic Shipping Co v Dillon (1993) 176 CLR 344.
There are two narrow exceptions. The first applies where the very object of the contract was to provide pleasure, relaxation or peace of mind. Building contracts do not fall within this category. The second applies where the breach causes real and substantial physical inconvenience, and the mental distress is a direct consequence of that physical inconvenience. This pathway is available in building disputes, but it requires actual evidence of actual physical conditions, not merely the general stress of a dispute.
Q. What is solatium and can an owner recover it in a building dispute?
A. Solatium is a term for damages awarded to compensate for emotional suffering, mental distress or injured feelings. It has a clearer basis in personal injury law than in contract law.
In a building dispute context, courts treat solatium claims as equivalent to distress and inconvenience claims. They apply the same test: the claim will only succeed if the owner can establish real and substantial physical inconvenience caused specifically by the breach, from which mental suffering directly followed. The label 'solatium' adds nothing. What matters is whether the legal prerequisites are met.
In Edwards v Sovereign Homes (QLD) Pty Ltd [2020] QCATA 146, the owner's solatium claim was rejected at QCAT and on appeal to QCATA precisely because those prerequisites were not established on the evidence.
Q. What does 'real and substantial physical inconvenience' actually mean for a building dispute?
A. The phrase comes from the 1875 English case of Hobbs v London and South Western Railway Co (1875) LR 10 QB 111. The court drew a distinction between mere annoyance, vexation or disappointment without physical consequences (not compensable) and genuine physical disruption producing physical effects (potentially compensable).
In a building context, the courts have accepted physical inconvenience claims where owners were compelled to continue living in premises undergoing significant remediation, exposed to dust, noise, loss of essential amenities or structural hazards over a prolonged period. The paradigm case is Watts v Morrow [1991] 1 WLR 1421, where owners who relied on a negligent survey had to live through months of disruptive repair works.
What does not qualify: frustration at the dispute process, disappointment at the quality of the finished product, stress from negotiations or litigation, or the general inconvenience of having a building dispute. The physical conditions must be causally connected to specific breaches of contract, not to the dispute itself.
Q. If an owner does succeed on a distress or inconvenience claim, how much can they recover?
A. Awards in this category are modest. Even in well-evidenced cases, English authorities (which Australian courts treat as persuasive on quantum) have placed the range for distress and inconvenience in building disputes at roughly a few thousand dollars per year of genuine physical exposure to the disruptive conditions.
Courts consistently moderate these awards by recognising that the suffering, while real, is transient. The award does not compensate for permanent psychological injury; it reflects the temporary disruption endured. A well-evidenced claim that succeeds in a Queensland domestic building dispute is unlikely to yield more than a few thousand dollars per year of exposure at most.
When you receive a cross-claim with a solatium or distress figure that looks large, consider the realistic quantum against this benchmark before treating it as meaningful exposure.
Q. Is a claim for 'loss of amenity' the same as a distress claim?
A. Not precisely. Loss of amenity is a conceptually distinct head of damage derived from the English House of Lords decision in Ruxley Electronics and Construction Ltd v Forsyth [1996] AC 344. In that case, a swimming pool was built to the wrong depth. The cost of rebuilding it was disproportionate and the diminution in market value was nil, yet the House of Lords awarded a modest sum for the loss of the 'consumer surplus' the client had contracted for.
The argument is that even where there is no financial loss and rectification is not reasonable, the owner has been deprived of something they specifically contracted for and that deprivation has value.
In Edwards v Sovereign Homes, the loss of amenity claim was rejected on its facts. The application of Ruxley-style loss of amenity in Queensland building disputes remains limited and underdeveloped. However, it is a separate argument that may be available in cases where specific contracted-for features are absent or materially deficient and rectification would be disproportionate. It is worth analysing separately from distress claims.
Q. Does the 2020 High Court decision in Moore v Scenic Tours change anything for builders?
A. Not in any practical sense for building disputes.
In Moore v Scenic Tours Pty Ltd [2020] HCA 17, the High Court unanimously confirmed that the Baltic Shipping categories remain good law in Australia. Damages for disappointment and distress from a contract to provide pleasure or relaxation are still available and are not personal injury damages subject to civil liability thresholds.
The Moore decision concerned a European river cruise. It confirmed the law for 'pleasure object' contracts, which remain the holiday and leisure cases. Building contracts are not in that category. The High Court's reaffirmation of Baltic Shipping leaves the framework unchanged for building disputes. Owners must still use the physical inconvenience pathway, with all its evidentiary requirements.
Q. What happened in Edwards v Sovereign Homes across the three proceedings?
A. The Edwards dispute began as a domestic building dispute in QCAT over Sovereign Homes' final payment claim of $46,155.20 under a standard HIA QC3 renovation contract. The owner made a cross-claim of over $133,000 including solatium, loss of amenity, delay damages and defect rectification costs.
At first instance (QCAT, 2018): Sovereign partially succeeded. The QCAT member found practical completion had been achieved on 11 December 2014, rejected the solatium and amenity claims, and ordered the owner to pay Sovereign's final claim plus interest, while also ordering Sovereign to pay the owner $79,938.30 for weather damage and defects. The owner was ordered to pay 70 per cent of Sovereign's costs.
On appeal ([2020] QCATA 146): The Appeal Tribunal dismissed the appeal and refused leave on all grounds. The distress damages conclusions were upheld.
In the Court of Appeal ([2022] QCA 4): The owner applied for leave to appeal on a single remaining question about the construction of the practical completion provisions in relation to weather damage works. The Court of Appeal dismissed the application with costs. The solatium and distress issues were not pursued at this level.
Q. What did the Court of Appeal actually decide in [2022] QCA 4?
A. The Court of Appeal (Fraser and McMurdo JJA and Davis J) dismissed the owner's application for leave to appeal from the QCATA decision. The application was confined to a single ground: whether the tribunal member had erred in law in finding that the weather-damaged works required a separate contract and that practical completion could be reached before they were repaired.
The Court refused leave on two grounds. First, the clause 24.9 deeming provision in the HIA QC3 contract operated to fix the date of practical completion. Because the owner had signed the Certificate on Practical Completion, expressed satisfaction at the meeting, and failed to give a written notice disputing the date within five working days, the deeming provision was triggered and the practical completion dispute was effectively foreclosed, regardless of the merits of the construction argument.
Second, even if the owner had succeeded on the construction point, the financial benefit of doing so was marginal relative to the costs of the appeal. The net outcome on remitter would have been a net order in the owner's favour of approximately $33,783, which did not justify the cost of the appeal proceedings.
Q. What is the clause 24.9 deeming provision in the HIA QC3 contract and why does it matter?
A. Clause 24.9 of the HIA Queensland Plain Language Alteration, Addition and Renovation Contract (QC3) provides that the date stated in the builder's last notice of practical completion is deemed to be the date of practical completion unless, within five working days of receiving that notice, the owner gives the contractor written notice (a) disputing the date and (b) detailing the reasons why the date is disputed.
If the owner does not issue that written notice within the five-working-day window, the deeming provision operates. The date is fixed as a matter of contract. The owner cannot later dispute it in litigation, even if they have an arguable position on the substantive question of whether practical completion had actually been achieved.
In Edwards, the owner signed the Certificate on Practical Completion, expressed satisfaction at the meeting, and sent messages the following day indicating willingness to pay. He did not issue a written dispute notice within five working days. The Court of Appeal held that this meant the clause 24.9 deeming provision conclusively fixed the date of practical completion in the builder's favour. This was decisive at the Court of Appeal level.
Q. Did the Court of Appeal decide whether weather damage before practical completion is within the builder's contract scope?
A. No. The Court found it was reasonably arguable that weather event damage to completed works before practical completion may fall within the contractor's contractual scope of works under clause 1 of the HIA QC3 contract, read alongside the insurance and extension of time provisions. Fraser JA expressly noted this without deciding the point.
The question was not decided on its merits because the clause 24.9 deeming mechanism made it immaterial on the facts of Edwards. The owner had failed to dispute practical completion within the required window, so the construction question could not affect the outcome.
This means the weather damage scope question remains open under the HIA QC3 form. If you face a dispute about whether pre-practical-completion weather damage falls within your original contract or requires a separate agreement, the Court of Appeal has neither confirmed nor rejected either position. Specialist legal advice is important before you take a position on this.
Q. What should a builder do at the practical completion stage to protect themselves under an HIA QC3 contract?
A. The Edwards case illustrates precisely what good practical completion practice looks like. At a minimum:
- Issue a written notice of practical completion in the correct form. This triggers the clause 24.9 clock. The notice must state the contractor's opinion of the date of practical completion.
- Conduct the inspection properly and document it. Walk through the works with the owner and agree on any minor defects in writing. The certificate should list those defects and the timeframes for rectification.
- Obtain the owner's signed acknowledgment. A signed Certificate on Practical Completion is strong evidence that the owner accepted practical completion at that date.In Edwards, the signed certificate was significant at every level of the litigation.
- Preserve all communications around the practical completion meeting. Text messages, emails and follow-up correspondence are all relevant. In Edwards, the owner's text messages the day after the meeting became part of the evidentiary record. Note if the owner does not dispute within five working days. If you receive no written dispute notice within the clause 24.9 window, that is a significant protection. Document that fact. If an owner disputes practical completion after the five-working-day window, what is the builder's position?
Under the HIA QC3 contract, if the owner does not issue a written notice disputing the date of practical completion within five working days of receiving the builder's notice, clause 24.9 deems the date stated in the builder's notice to be the date of practical completion. This is a contractual deeming provision, not merely a procedural rule.
As confirmed in Edwards v Sovereign Homes [2022] QCA 4, this means the owner cannot later relitigate the practical completion date in tribunal or court proceedings, even if they have an arguable position on whether completion had genuinely been achieved. The deeming provision operates as a matter of contract construction.
If an owner attempts to raise a late dispute about practical completion after the window has passed, the builder's position is that clause 24.9 applies and the date is fixed. That argument should be advanced clearly in your defence and in any subsequent submissions.
Q. What should a builder do if works are damaged by weather before practical completion?
A. The Edwards case left this question open but flagged it as genuinely uncertain under the HIA QC3 form. Several steps are prudent.
First, notify the owner in writing about the damage and the insurance claim as soon as practicable. In Edwards, the builder notified the owner of the insurance claims. The owner was aware those claims would need to be settled before repair works could be completed. This factual finding was important.
Second, consider whether you are entitled to an extension of time under clause 16. Weather events beyond the contractor's sole control that were not reasonably foreseeable may qualify as a claimable delay.
Third, get legal advice before issuing a notice of practical completion if substantial weather damage remains unrepaired. The Court of Appeal found the construction argument about whether such damage falls within the original contract scope was reasonably arguable. How you characterise the position, and whether you issue a practical completion notice at all while significant damage remains, is a decision that carries legal risk either way.
Fourth, keep all insurance correspondence, claim documentation and communications with the owner about the weather events on file. If the matter is later disputed, that evidence will be important.